All clients have different requirements, time scale and abilities, so I am flexible in how an agreement can be formulated. My fees and costs can be charged either as a percentage of the cost of the work and materials 7 – 10% for new work or 10 – 14% for existing buildings, or on a time basis.

For all projects the fees need to be discussed and agreed with the client in advance.


TYPICAL EXAMPLE 1 - RENOVATION & CONVERSION COSTS

Les Hautes Mesleries, Normandy - 225sqm on 3 floors
 

no.

DESCRIPTION OF WORK
 

£


1


BUILDERS WORK
& strip out barn and clear away all redundant materials, construct new first and mezzanine joisted floors. Labour cost for clearance.
 


600.00

2

EXTERNAL GROUND WORKS - Laying & excavation of new pipes for rainwater drainage to soak-away & soil pipes to new Fosse Septique [septic tank Biological]
 

3,300.00

3

DORMER WINDOWS - 6 no openings & slate pitched roofs
 

2,900.00

4

INSULATION, RENDERING & PLASTERING - To roof void, solid walls, new plasterboard ceilings and partition walls.

New roof insulation - 150mm composite boards.
 

3,500.00

5

NEW TIMBER FLOORS - 200mm rough oak boards sanded & polished.
 

1,600.00

6

Form new door - openings & frames to internal rooms.

 

1,000.00

7

PLUMBING - New sanitary fittings & brassware
 

 4,500.00

8

ELECTRICAL - Supply & install new power cable distribution, brass accessories, lighting.
 

2,500.00

9

JOINERY supply & fit - New solid oak staircase with winder.

6 no dormer windows, double glazing & linings.
 

5,100.00

 

10

SOLID OAK WINDOWS & DOORS - Supply & fit :-

6 no windows & chestnut sills.
2 no entrance doors & frames.
2 no sets of French windows & frames.
 

3,800.00

11

Floor & wall tiling to two bathrooms, kitchen and total ground floor.[ 75 sq m]
 

3,300.00

 

12

Decoration - Internal partitions and ceilings.
 

1,500.00

13

Floor coverings - Sisal matting & rugs.
 

700.00

14

Utilities - Service connections for metered water, electricity and propane gas supply tank.
 

850.00

15

Fittings - Wood burning stove, Reyburn cooker, including flue linings and insulation & all white goods.
 

4,050.00

 

16

Furniture - Beds, dining table, chairs sofa’s, kitchen cupboards etc.
 

2,500.00

17

Soft furnishings - Curtains and bed linen.
 

450.00

18

Fees - Notaries & agents.
 

4,800.00

19

Travel costs - Ferry trips & fuel costs.
 

3,000.00

20

Time input - Site supervision, painting & decorating, making internal doors, basic joinery etc.
 

15,000.00

 


Grand total expenditure
 


£63,950.00


 