All clients have different requirements,
time scale and abilities, so I am
flexible in how an agreement can be
formulated. My fees and costs can be
charged either as a percentage of the
cost of the work and materials 7 – 10%
for new work or 10 – 14% for existing
buildings, or on a time basis.
For all projects the fees need to be
discussed and agreed with the client in
advance.
TYPICAL
EXAMPLE 1 - RENOVATION & CONVERSION
COSTS
Les Hautes Mesleries, Normandy -
225sqm on 3 floors
|
no. |
DESCRIPTION
OF WORK
|
£ |
|
1 |
BUILDERS WORK
& strip out barn and clear away
all redundant materials,
construct new first and
mezzanine joisted floors. Labour
cost for clearance.
|
600.00 |
|
2 |
EXTERNAL GROUND WORKS
- Laying & excavation of new
pipes for rainwater drainage to
soak-away & soil pipes to new
Fosse
Septique [septic tank
Biological]
|
3,300.00 |
|
3 |
DORMER WINDOWS
- 6 no openings & slate pitched
roofs
|
2,900.00 |
|
4 |
INSULATION, RENDERING &
PLASTERING
-
To roof void, solid walls,
new plasterboard ceilings and
partition walls.
New roof insulation - 150mm
composite boards.
|
3,500.00 |
|
5 |
NEW TIMBER
FLOORS - 200mm
rough oak boards sanded &
polished.
|
1,600.00 |
|
6 |
Form new door
- openings &
frames to internal rooms.
|
1,000.00 |
|
7 |
PLUMBING
- New sanitary fittings &
brassware
|
4,500.00 |
|
8 |
ELECTRICAL
- Supply & install new power
cable distribution, brass
accessories, lighting.
|
2,500.00 |
|
9 |
JOINERY
supply & fit - New solid oak
staircase with winder.
6 no dormer windows, double
glazing & linings.
|
5,100.00
|
|
10 |
SOLID OAK WINDOWS & DOORS
- Supply & fit :-
6 no windows & chestnut sills.
2 no entrance doors & frames.
2 no sets of French windows &
frames.
|
3,800.00 |
|
11 |
Floor & wall tiling
to two bathrooms, kitchen and
total ground floor.[ 75 sq m]
|
3,300.00
|
|
12 |
Decoration
-
Internal partitions and
ceilings.
|
1,500.00 |
|
13 |
Floor coverings
- Sisal matting & rugs.
|
700.00 |
|
14 |
Utilities
-
Service connections for metered
water, electricity and propane
gas supply tank.
|
850.00 |
|
15 |
Fittings
-
Wood burning stove, Reyburn
cooker, including flue linings
and insulation & all white
goods.
|
4,050.00
|
|
16 |
Furniture - Beds,
dining table, chairs sofa’s,
kitchen cupboards etc.
|
2,500.00 |
|
17 |
Soft furnishings
- Curtains and bed linen.
|
450.00 |
|
18 |
Fees
-
Notaries & agents.
|
4,800.00 |
|
19 |
Travel
costs
-
Ferry trips & fuel costs.
|
3,000.00 |
|
20 |
Time input
-
Site supervision, painting &
decorating, making internal
doors, basic joinery etc.
|
15,000.00 |
|
|
Grand total expenditure
|
£63,950.00 |
|
|